|
The
management of the process by which an owner, once having identified the need
for a Capital Project, successfully accomplishes the tasks of project goal
formulation, design, construction and placing in operation of that project,
has some confusing terms for the inexperienced owner, especially in the
construction activities portion of the project. This article focuses on the
construction phase of the project.
We are assuming that the Owner, if not well-informed in the area of design and
construction, has hired an Owner's Representative or Development Manager, to
act as the Owner's knowledgeable expert in coordinating and completing the
tasks. They are the Owner's first line of defense against the inherent risks
of any design and construction project.
While a good Owner's Rep should be able to assess and recommend the
appropriate contract format to Ownership, any responsible owner should
understand the implications and associated risks in undertaking any contract.
The construction phase begins early in today's projects, mainly due to the
increased awareness of the time-cost of money and the need to bring projects
online quicker, hence the "fast-tracking", or accelerated phasing,
of many projects. A qualified Owner's Rep has enough expertise in construction
activities to be able to identify at what point in the project's progress it
will be most cost-beneficial to bring the "Constructor" into the
fold of the team, and under what contract format this will be done.
The industry has developed two main types of construction entity: the General
Contractor and the Construction Manager.
Once construction evolved out of the Agrarian Era, during which time a large
percentage of buildings required nothing more than the owner's self-labor to
construct his dwelling, the "public institutions" such as the king
or the church had their "Master Mason's" or Master Builders".
Since then, the roles and titles of the various specialized team members began
to evolve and change.
As the Industrial Era dawned, the "user" began moving further and
further away from the "source" of the creation of a facility. The
Master Mason was replaced by the Master Builder. The Master Builder was more
intelligent and experienced than the tradesmen working directly on building
materials, and could do more than the Master Mason, but had learned to
delegate more and more of the specialties to "specialists". He
coordinated them within his overall "grand plan", and the Owner got
his facility built.
In today's design/construction milieu, any Capital Project involves a team of
specialists who design it, build it, furnish it and put it into operations for
the "users". The "construction" of the project is
typically the largest financial investment portion of the project.
Construction as it is practiced in the U.S. today, has evolved over the past
twenty to twenty-five years from the basic
Owner-working-with-Architect-and-General Contractor (GC) format to the more
prevalent Construction Management process that it is today.
General Contractor (GC)
This term historically represented a construction
firm, who had in it's direct employ a sufficient number of personnel with
experience in a multitude of construction trades, i.e. carpenters, masons,
electricians, plasterers, plumbers, general laborers, mechanical, etc., etc.
In addition they had senior personnel acting as Project Mangers,
Superintendents, estimators and procurement specialists. The GC took on a
construction project on a fixed price (Lump Sum), a cost-plus price, or a
unit-price basis, and was the entity financially at-risk for completing the
project within this cost agreement. General Contracting, in this true sense of
the original meaning, has all but disappeared in today's construction milieu.
Due to the vagaries of the market, when General Contractors began to have a
more difficult time maintaining a large, diverse base of tradesmen as
employees, they found it more expeditious to "sub-contract" various
trades to specialist contractors in various fields. As the specialist field
became more varied and diverse the GC's began to rely more and more on
sub-contracting. Under their GC types of contracts, they were still at-risk to
deliver, and had responsibility for their "Subs" completing their
contractual obligations.
Construction Manager (CM)
As
construction projects became even more complex, GC entities saw that they
could market their skills as the "Manager" of the Construction
process, hence the term Construction Managers. They reduced their employees to
Senior Management staff, Project Managers, estimators, Project
Superintendents, and a core of Laborers. All of the actual construction work
was sub-contracted to the specialty contractors mentioned above. The CM's
"contracted" with the subs, but the CM was still the
"Contractor" or "Constructor", responsible for the
coordination and completion of the work and at risk for the same. Within the
CM format, there are two basic forms of the contract with the Owner: "CM
as Agent" (CMa) and "CM as Constructor" (CMc). The basic
premise of the CMa format is that all of the sub-contracts "run to"
the Owner, who is responsible only for paying the "Subs" directly.
This in itself, although mistakenly assumed by many, does NOT make the Owner
the "General Contractor" in terms of expertise, knowledge,
coordination or management of the subs. The CMa is still responsible and
"At-Risk" for the "construction" management and the
day-to-day activities of the subs. The CMa is responsible for quality, cost
and schedule. The second, CMc implies that the CMc is "contracting"
directly with all of the Subs and is responsible for paying the
subcontractors. The CM is still responsible for all of the construction
activities. The Owner pays only the CM. For the Owner who has the staff
infrastructure to handle the accounting tasks of paying and tracking multiple
payments to a multitude of "Sub-contractors", the "Agency"
format has potential savings in that the CMa fee is significantly lower than
the CMc fee.
The General
Contractor format has become the exception in highly urbanized areas. It
is usually found only in minor to medium commercial work, and even there it is
the exception rather than the rule as many so-called GC's actually
"sub" out much of the work. However the term is still used and has
become indicative of the format in whereby the GC has the responsibility for
all of the sub-trades in both the "contractual" as well as the
coordination. The GC format may be most appropriate for a project where all of
the elements are fairly straight-forward and/or repetitive.
As this system of doing construction work took hold in the industry, related
professional groups began to take this form of contracting more seriously, and
had their "contract" departments begin to formulate
"standard" contract forms for their members to use with their
clients. These are to be found in the American Institute of Architects (AIA),
Association of General Contractors (AGC), and the Construction Management
Association of America (CMAA).
Within these formats are sub-formats that define the risk/reward relationships
and lines of responsibility. GC or CM contracts can be Lump Sum, Cost-Plus or
a Guaranteed Maximum Price (GMP). Unit pricing can be used in all of these for
many purposes. Each project must be analyzed for complexity, uniqueness,
time-constraints, award policies, normal vs. fast-tracking, etc., to determine
the best composite of formats.
The advantages to using the CM format are in enabling the CM to being brought
in at an early stage when their expertise in construction-related items can be
brought to bear in the value engineering, Constructibility and cost/benefit
studies for proposed systems and materials. They enable the design consultants
to test theories and potentials, they help the owner to choose life-cycle
maintenance benefits of systems and help to refine construction schedules.
An important item to keep in mind is that the CM format in itself is does not
provide an Owner with the overall Project expertise that is needed in any
major Capital Project. An Owner's Representative or Development Manager best
provides that. Owner's Representation or Development Management refers to a
much more comprehensive service that manages the entire Capital Improvement
Program process professionally, efficiently and safely.
Chasan • Nicoletti Inc. is an
Owner's Representative firm providing Capital Program Project
Management. It was formed in New York in 1985 by Alan D. Chasan and has completed many projects for Owners and Tenants alike in
its 16-year history. CNI has completed over $175 million in Capital Improvement
Projects Management in the U.S.. Our staff is thoroughly experienced and
qualified to provide PM services and maintain CNI's ethical and
professional level of protecting Owner's interests.
|